Project Map › The land and its rules

Start here

The land and its rules

Before you fall for the view, meet the rules that come with it: zoning, the area plan, overlays for fire, faults and scenery, easements, and whether you need a planning permit or only a building permit. Most of it is free to look up, if you know where.

Who's involved
The county's Housing and Community Development department (planning and building), your title company and a land surveyor.
What it shapes
What you can build, how big and how tall, where on the lot, and whether you'll face a public hearing.
When it matters most
Before you make an offer. Everything else builds on this.

Your 15-minute parcel check

All free, all from the county, and all you need is the parcel number (APN) from the listing or tax bill.

1. Parcel Report

Enter the APN to get the parcel's zoning, land use, potential hazards, critical habitat and historical resources in one report.Source

Open the Parcel Report →

2. Permit and code case history

Search the county's permit portal by address or parcel for past permits, planning applications and open code cases. No account is needed.Source An open violation can hold up permits for the next owner, too.Source

Search the permit portal →

3. Hazard maps

The county's map tools include geologic hazards (erosion, liquefaction, landslide, seismic), archaeological sensitivity, and fire protection areas.Source

County GIS and maps →

4. A call to the Permit Center

With your APN, a permit technician can tell you setbacks, height limits and which permits your project will need.Source

(831) 755-5025 · 1441 Schilling Place, Salinas

Which area plan are you in?

Monterey County's General Plan is divided into area plans, each with its own policies. The coast has its own land use plans under the Coastal Act.Source

Which permits will you need?

This is where most people get lost, so start with the big picture. Every new home needs a building permit. Some lots also need a planning permit first, and that one decides whether your timeline is months or years and whether neighbors get a say. One call to the Permit Center with your APN (the parcel number on your tax bill) tells you which path you're on.

Call the Permit Center with your APN A · Building permit only B · Planning permit first Submit building plans Plan check: building,fire, Environmental Health Building permit issued Build, with inspections Meet a planner, apply;30 days to deem complete Environmental review(CEQA), if needed Staff decisionAdministrative Permit,most Design Approvals or Public hearingUse Permit, Variance,Combined, Coastal Dev. 10-day appeal window(longer on the coast) Meet conditions of approval,then go to Path A Can't meet one?Minor or full amendment,or an extension Path B can take months, sometimes years. Ask which path you're on before you buy.
Simplified from the county's planning process and zoning code. Tap a permit name to see what it means. A staff decision can still become a hearing if it's triggered (see below). Coastal permits have an extra appeal window to the Coastal Commission.Source

What each permit means

Find the ones the Permit Center named for your parcel:

PermitWhen you need itWho decidesPublic hearing?2026 planning fee*
Building permitEvery new home. Plan check by building, fire and Environmental Health.County staffNoBased on the value of construction. Use the estimator.
Design ApprovalIn design-control zones (a D, S or VS in your zoning): new buildings, additions, fences, even exterior color changes.SourcePlanning staff for simple projects. Complex ones go to the local Land Use Advisory Committee and the Zoning Administrator.Only for complex or controversial projects$640 over the counter
$1,210 staff review
$3,750 with a hearing
Administrative PermitUses your zoning lists as needing one.SourcePlanning Director or Zoning AdministratorNot unless triggered (see below). Neighbors within 300 feet are still notified.$6,860
Use PermitUses your zoning lists as needing one, and building on slopes over 25%.SourceZoning Administrator or Planning Commission, depending on the useAlways$12,460
VarianceRelief from setbacks, height, lot coverage or building site size, when your lot's size, shape or slope makes the rules unfair.SourceZoning AdministratorAlways$5,870
Combined Development PermitWhen you need two or more planning permits. It bundles them into one application and one hearing.SourceWhoever decides the main permit. If any part goes to the Planning Commission, it hears the whole thing.Always$17,930
Coastal permitsAnything in the coastal zone. Most projects get a Coastal Exemption. Others need a Coastal Administrative Permit or a full Coastal Development Permit.SourceCoastal Planning staff, or the Zoning Administrator or Planning CommissionYes for a Coastal Development Permit, with an extra appeal window to the Coastal CommissionCoastal Development Permit $12,510
Certificate of ComplianceTo confirm, or fix, that your parcel is a legal lot.SourceCounty staffNoAsk the Permit Center

*The planning department's fee alone, from the schedule the Board of Supervisors adopted on February 3, 2026, in effect since April 4, 2026.Source County Counsel adds its own fee (for example, $680 on a Use Permit). Environmental Health, Public Works and your fire agency charge separately, and a 13% technology fee goes on top.

When an Administrative Permit turns into a hearing

An Administrative Permit is decided by staff after notice to neighbors within 300 feet, in the mail, on posted signs and in the newspaper, at least 10 days ahead. It goes to a public hearing before the Zoning Administrator if staff recommends denial, the project isn't exempt from environmental review, you ask for one in writing, someone files a substantive written request, or there are zoning violations on the property. It can't be denied without a hearing. Once your application is complete, the county has 15 working days to act or set a hearing, or the permit is deemed approved.Source

Use Permits, Variances and Administrative Permits all require a finding that the property complies with zoning and that any violation cleanup costs have been paid.Source Approved permits stay valid as long as construction starts within two years.

What do planning permits cost?

More than the "application fee" suggests. Each department that reviews your project (planning, County Counsel, Environmental Health, Public Works, your fire agency) charges its own fee. Many also charge a second "condition compliance" fee after approval, and environmental review is billed on top.Source The county adopted new land use fees in 2026, effective April 4.Source Use the county's 2026 Land Use Fee Estimator, which includes the other departments, on its Permit Fees & Types page.

Our experience: We remembered being quoted about $12,000 for a Use Permit. The 2026 schedule says $12,460, and that's just the planning department's share. Add County Counsel's $680 and the 13% technology fee and you're near $14,800 before Environmental Health, Public Works, your fire agency or any environmental study sends a bill. It's the kind of number nobody mentions until you ask.

Planning fees are the small part. See the full cost picture →

When the plan doesn't go to plan

A planning permit can take months, and sometimes years. Here's what happens when you can't meet a condition, when the clock is running out, or when the county is the slow one. Short version: there's almost always a next step. It usually comes with a form and a fee.

If you can't meet the conditions of approval

Conditions are the to-do list attached to your approval: a study, a road improvement, a landscaping plan, a recorded agreement. If one turns out to be impossible or far too expensive, you aren't stuck with Path A or nothing. Your options:

Don't just skip one

No building permit is issued except in line with your planning permit's conditions. If conditions aren't met after the fact, the county can modify or revoke the permit after a public hearing.Source Checking that you've met them costs money too: $210 per condition after the first three, and $420 per environmental mitigation measure.Source A permit with 15 conditions has a compliance bill of its own.

When your permit is about to expire

Permits come with a clock, and the county taking its time doesn't stop yours. Know your dates, put them in your calendar, and ask for more time before you need it.

PermitHow long it lastsHow to extend it2026 fee
Use Permit (and most planning permits)Whatever date the permit states. If none, it stays valid as long as construction starts within two years of approval.SourceA written request, with your reasons, filed at least 30 days before it expires. It goes back to whoever approved the permit, with notice.Source Miss that window and you may be starting over.$1,960, plus $340 County Counsel on a Use PermitSource
Building permitState law: it expires if work doesn't start within 12 months of issue.Source Long gaps between inspections can also lapse it, so ask the county what counts as active.Ask in writing, with a good reason. The building official can grant extensions of up to 180 days at a time.Source$416Source

A dead permit isn't just paperwork. Starting work after it expires counts as working without a permit, and the county charges double the permit fee for that.Source

When the county is the slow one

State law puts some deadlines on the county, too. They don't make anything fast, but they give you something to point to:

These laws have exceptions, and whether one applies to your project is a legal question. In practice, what helps most: answer every correction letter fast and completely, keep a written log of every submittal and response, ask your planner for a target date in writing, and request your extension early rather than hoping the county finishes first. If the delays are costing you real money, that's the time to talk to a land use attorney.

  1. 1

    Before you buy

      What we learned

      The previous owners' planning history was the best due diligence we got. Past applications, even failed ones, told us exactly which studies and issues to expect.

    • 2

      Can I build here?

      • 3

        Design

        • 4

          Permits

          • 5

            Build

            • 6

              Move in and beyond

              Real numbers

              WhatCostSource
              County planning and building feesSee the county's current fee schedule and estimatorCounty fees
              Boundary surveyNo reports yetShare yours
              Studies inherited from previous ownersRoughly $20,000 to $40,000 of work at today's pricesUs, 2026

              Sources

              Every fact above links to its source. Checked November 26, 2026, and rechecked monthly.

              Not legal advice. Title, easements and lot legality are legal questions, so have a title officer or real estate attorney review yours.

              See also Access (legal access and the 25% slope rule) and Fire safety (fire setbacks).