Project Map › Money and team
Plan for it early
Money and team
What it really costs to get from raw land to a building permit, who you'll hire along the way, and the bills nobody mentions until they arrive. Fair warning: this is Monterey County. Bring snacks, and a checkbook.
- Who's involved
- You, a lender, a surveyor, engineers and designers, maybe a land use consultant, and a licensed contractor (or you, as an owner-builder).
- What it shapes
- Whether the project is possible at all, and how long you can keep paying while the county does its part.
- When it matters most
- Before you buy. The price of the land is often the smallest number you'll see.
The cost of getting permission
Before anyone pours a foundation, you pay for studies, designs, fees and reviews. We call it the cost stack. Some layers have official prices. Others depend entirely on your land, and the only honest numbers are real quotes. Here's each layer, and where its numbers come from:
| Layer | What's in it | What we know | Where the number comes from |
|---|---|---|---|
| Planning permit (only on Path B) | Whichever planning permit your lot needs: a Use Permit, Administrative Permit, Variance or one of the others. See what each permit means. | A Use Permit is $12,460, plus $680 County Counsel, plus a 13% technology fee: about $14,800 before other departments. An Administrative Permit is $6,860. | County 2026 fee scheduleSource |
| Environmental review (if needed) | The county checks every application against the state's environmental law (CEQA). One new house is usually exempt,Source but sensitive habitat, steep slopes or other unusual conditions can mean an Initial Study, or a full Environmental Impact Report on harder projects.Source | County deposits start at $15,000 for an Initial Study and $20,000 for an EIR. Consultants are billed on top. | County 2026 fee scheduleSource |
| Building permit and plan check | Building, plus Public Works and your fire agency. Environmental Health's share is in the next row. | Based on the value of construction, so it grows with the house. Use the county's 2026 Land Use Fee Estimator. | County fee estimatorSource |
| Septic and well permits | Environmental Health's own permits and reviews, for land with no sewer or water main. | Perc and soils testing: $1,039 deposit. Septic permit: $2,394 for a conventional system, $4,399 for an alternative one. Well permit: $3,920, plus $1,042 to $1,561 to witness the yield test. Their review of your building permit: $1,206, or $2,412 on a planning permit. Extra time runs $259 an hour. | County Environmental Health fees, July 2026Source |
| School impact fee | Charged per square foot of new living space and paid to your school district before the building permit is issued. | The state's basic cap rose to $5.38 per square foot in 2026. A 2,000 sq ft house: up to about $10,760. Some districts charge more with a special study. | State Allocation BoardSource Ask your district for its rate. |
| Regional traffic fee | A countywide fee on new homes that pays for regional road projects. | Today about $2,400 to $5,000 per house, depending on the zone. A 2026 update could raise it to as much as $15,000 to $31,000. See below. | Transportation Agency for Monterey CountySource |
| Studies and reports | Survey, soils (geotechnical), perc test and septic design, and when triggered: biology, arborist, archaeology, hydrology, traffic. | Depends entirely on your land. Our inherited studies were roughly $20,000 to $40,000 of work at today's prices. | Real quotes. Our box of reports |
| Design and engineering | House plans, structural and civil engineering, energy calculations, grading and drainage plans. | No reports yet. | Share yours |
| Conditions and mitigation | Whatever your approval requires: road work, plantings, monitoring, plus the county's fees to check them off. | Condition checks are $210 each after the first three, and $420 per environmental mitigation measure. The work itself is extra. | County 2026 fee scheduleSource |
Our home design team told us to plan on about $200,000 to take our project through the county from start to finish. That's studies, permits and fees. It doesn't include designing the house, architecture or engineering, and it certainly doesn't include building anything. Yes, really. Welcome to Monterey County. It's also why we started this guide.
The Transportation Agency for Monterey County updates its regional fee every eight years, and the 2026 study shows much higher maximums for a single-family home:Source
| Zone | Today | 2026 study maximum |
|---|---|---|
| North County | $4,925 | $29,677 |
| Greater Salinas | $4,128 | $31,199 |
| Peninsula and South Coast | $5,029 | $15,341 |
| South County | $2,415 | $27,354 |
| One countywide zone (an option on the table) | $4,135 average | $22,440 |
These are maximums, not adopted fees. Staff recommended raising current fees by 35% to 65%, and the agency's board and then the cities and county still have to approve the result. If your building permit will be issued in the next year or two, ask the Permit Center which rate applies to you.
The low end is predictable: a building permit, impact fees and a few required reports. The high end isn't. One sensitive species, a slope over 25% or an Environmental Impact Report can each add tens of thousands of dollars and a year or more. Anyone who quotes you a single number for "permits" without seeing your parcel is guessing. Ask for the county's fee estimate, and a written scope and price for each study.
Bills nobody mentions
Your team, and when to hire them
You'll hire most of these people before you ever see a contractor. Check every license on the state's free lookup before you sign anything.
| Who | What they do | When | License to check |
|---|---|---|---|
| Land surveyor | Finds and marks your boundaries, maps the slopes (a topographic survey), stakes the house. | Before you buy, if the corners aren't marked | Licensed land surveyorSource |
| Geotechnical engineer | The soils report: what the ground can hold, landslide and drainage risk. | Feasibility, before design | Civil or geotechnical engineerSource |
| Septic designer | Perc tests and the septic design. See Wastewater. | Feasibility | A qualified professional under county code. Ask Environmental Health who qualifies. |
| Specialists, if triggered | Biologist, arborist, archaeologist, hydrologist, traffic engineer. | When the county asks, often during planning review | Varies. For biology, paleontology and historic reports, the county keeps an approved consultants list. |
| Designer or architect | The house plans. California doesn't require an architect for a wood-frame home of up to two stories plus a basement, but any part that isn't conventional framing needs an architect's or engineer's stamp. Hillside homes often do.Source | Design | Architect, if you use oneSource |
| Civil and structural engineers | Grading, drainage, driveway and retaining walls (civil); foundations and framing (structural). | Design | Civil or structural engineerSource |
| Land use consultant or permit expediter | Shepherds a planning permit through the county. Optional, and no state license exists for it, so ask for references from recent county projects. | Planning, if you're on Path B | None. References instead. |
| Well driller | Drills the well. This is one trade you can't do yourself, even as an owner-builder.Source | Feasibility or build, after the well permit | C-57 well drilling contractorSource |
| General contractor | Builds the house and manages the trades. | Late design, so they can price it before plans are final | General building ("B") contractorSource |
Good land use consultants are busy. Expect to push, push, push them along, and then they push, push, push the county along. Agree on check-in dates up front, and ask every time: what are we waiting on, and who has it?
Anyone you pay $1,000 or more for a job, counting labor and materials, or for any work that needs a building permit, must hold a contractor's license.Source Splitting a big job into small invoices doesn't get around it.
Thinking about being your own builder?
It's legal, and it can save money. It also moves the contractor's risks onto you. California lets an owner build without a license in three main ways:Source
When you apply for the building permit, you sign an Owner-Builder Declaration under penalty of perjury.Source A few things in it surprise people:
- Selling soon is a red flag. Sell within a year of finishing and you have to prove you didn't build it to sell.Source
- You may become an employer. Hire an unlicensed helper and you're responsible for workers' compensation. Going without it can bring criminal penalties and fines up to $100,000, on top of the injury costs.Source
- The lender is on the form, too. The permit application asks for your construction lender, so talk to lenders about owner-building before you commit to it.
Paying for it
Land, construction and the finished house are usually financed differently, and rural parcels can narrow your choices. There's no single right answer, so here's what to ask before you buy:
Questions for a lender
- Do you lend on raw land in unincorporated Monterey County? How much down?
- Do you offer construction loans, and do they convert to a regular mortgage when the house is done?
- Do you lend to owner-builders, or only with a licensed general contractor?
- What do you need to fund: approved plans, a building permit, a fixed-price contract?
- Will you lend on a home with a well, septic, solar and propane instead of utilities?
- If you're a veteran: do you make VA construction loans, ideally a single loan that converts to a VA mortgage when the house is done? Not every VA lender does, so ask early.
- What insurance do you require during construction and after, and will you accept a California FAIR Plan policy?
Questions for yourself
- How long can we pay holding costs if planning takes two years instead of six months?
- What's our contingency for surprises in the ground?
- If the regional traffic fee or other fees rise before our permit, can we absorb it?
- Can we get fire insurance on this parcel, and what if only the state's last-resort plan will cover us? See Fire safety.
- 1
Before you buy
- 2
Can I build here?
- 3
Design
- 4
Permits
- 5
Build
- 6
Move in and beyond
Real numbers
| What | Cost | Source |
|---|---|---|
| Studies inherited from previous owners | Roughly $20,000 to $40,000 of work at today's prices | Us, 2026 |
| Use Permit, planning share with County Counsel and technology fee | About $14,800 | County, 2026 |
| Design and engineering | No reports yet | Share yours |
| Cost to build, per square foot | No reports yet | Share yours |
Sources
Every fact above links to its source. Checked November 26, 2026, and rechecked monthly.
Not legal, tax or financial advice. Fees change, and your parcel decides which ones apply. Get the county's estimate and a lender's answers in writing.
See also The land and its rules (which permits you'll need) and Fire safety (insurance).