Project Map › Power

Deal-breaker #5

Power

Bringing PG&E to raw land, the solar the state requires on every new home, and keeping the lights (and the well pump) on when the grid goes dark. Out here, the power company can be a very long extension cord away.

Who's involved
PG&E, a licensed electrician and solar installer, the county (permits and inspections), and your fire agency (solar and generator signs).
What it shapes
Your budget more than anything. The distance to the nearest line, and your all-electric or propane choice, both change the price.
When it matters most
Before you buy, then early in design. PG&E runs on its own timeline.

This tailors the page and your Project Map. Saved on this device only.

Power in Monterey County, in four facts

PG&E line, often in the driveway trench PG&E METER Main panel Solar: roof, carport or ground Inverter Battery Generator Transfer switch House Well / booster pump
A simplified sketch, not a wiring diagram. Many rural homes combine all of these: PG&E service, the solar the code requires, a battery, and a generator for long outages. The transfer switch keeps generator power from flowing back into PG&E's lines, which protects line workers.Source
Propane and PG&E: two different bills

Out in the country there's usually no natural gas line in the road, so the real choice is all-electric or electric plus propane. Propane means a tank near the house, filled by a delivery truck, with fuel bought at market prices. That's one bill.

The second bill is easy to miss. To bring electricity to your house, PG&E extends its line from the nearest pole, and normally it pays part of that cost for you (an "allowance"). Since July 1, 2024, PG&E doesn't give that help to new homes that also use propane or natural gas. You pay the full cost of the electric line. All-electric homes still get the help.Source

In plain terms: a propane range or water heater can raise the price of your electric hookup, on top of the cost of the propane itself. Ask PG&E for estimates both ways before you choose. That propane range may cost more than it looks.

Ways to cut the cost of bringing power up the hill

PG&E doesn't have to do all the work, and on a long driveway the split matters.

You dig the trench, PG&E pulls the wire

For underground service, PG&E's own rules have the homeowner provide the trench, conduit and backfill. PG&E furnishes and installs the service cable and makes the connection.Source Your contractor can do that trenching, ideally at the same time as the driveway, water line and internet conduit, so you dig once. It has to meet PG&E's specs, including at least 24 inches of cover over the conduit and compacted backfill. On services of 75 feet or more, talk to PG&E before you buy conduit. Long runs often need bigger conduit for bigger cable.

Meter near the road, your own line up the hill

Some rural owners ask PG&E to end its service and set the meter near the road. Their electrician then runs a private line from the meter up to the house. PG&E must review and approve every meter location, and it asks you to consult its project coordinator early in planning, so this is a question for PG&E, not a given.Source

Everything past the meter is yours. It's installed by a licensed electrician under a county electrical permit, and you maintain it forever.Source The catch is distance. Electricity loses voltage over a long run, so a line hundreds of feet up a hill needs much heavier wire, and that adds cost. Have your electrician price that private run against PG&E's quote for bringing service all the way up. Sometimes it's cheaper, and sometimes it isn't.

Ask PG&E's project coordinator

Should you go off-grid?

It's a fair question when PG&E's line is a long, expensive way off, or when you're tired of fire-season shutoffs. Here's what we could confirm, and what you'll need to ask.

Is it legal?

Yes, with a permit. California counties permit off-grid homes. The building codes ask that the system provide power equivalent to a utility service. Neighboring Santa Cruz County spells this out: an off-grid system must be permitted before construction, designed by a licensed solar contractor, and include a 100-amp panel and an outside disconnect.Source

Monterey County doesn't publish off-grid design standards that we could find. Ask the Permit Center what it will require before you design.

If PG&E's line is at my property, do I have to connect?

We found no county rule requiring a home to hook up to PG&E. That's different from sewer, where the county requires a connection if a main is within 300 feet and your lot fronts that street.Source In practice, PG&E extends service when you apply and pay. If you don't apply, it doesn't come. Confirm with the Permit Center for your parcel, since a rule we didn't find would still apply to you.

One thing to weigh: connecting later can cost more than connecting during construction, especially once your driveway and landscaping are finished.

Isn't there a rule about being too far from the grid?

Not one that decides it for you. The choice is yours, and the deciding factor is usually cost: you pay for most or all of a long line extension.Source You may hear about PG&E's "Remote Grids." These are standalone solar, battery and propane-generator systems that PG&E builds in high fire-threat areas to replace long power lines for eligible customers. PG&E pays for and maintains them, and customers keep their usual PG&E rates. PG&E chooses where they go, so it isn't a way for a new home to opt out, and you shouldn't plan around one.Source

Do I still have to meet the solar requirement?

We found no off-grid exception in the state's 2025 solar FAQ, so plan on meeting it.Source An off-grid home needs a solar array anyway, usually a bigger one than the code minimum. Have your energy consultant confirm how it's documented.

How big a system, and is it enough?

As one benchmark, Santa Cruz County's minimum off-grid design for a single-family home is a 2 kW solar array, 12 kWh of usable battery and a 7 kW inverter, built around just 4 kWh a day of winter use.Source That's a floor, not a comfortable family home. Well and booster pumps, heat pumps and an electric range all push it far higher, and short, foggy winter days cut solar output just when you need it.

What about redundancy?

Off the grid, you are the power company. Plan for three layers: solar for every day, batteries for nights and cloudy stretches, and a generator for long gray weeks or a failed part. The pumps that move your water are the loads you can't let fail. Remember that firefighting water may also depend on them.

Three ways to power a rural home

PG&E + required solarPG&E + solar + batteryOff-grid
Upfront costPG&E extension plus solarExtension, solar and batteryBigger solar, large battery and generator, but no extension
During a PG&E shutoffLights out, unless you add a generatorBattery keeps essentials runningUnaffected
Who fixes problemsPG&E (the line) and you (the solar)PG&E and youYou
OngoingMonthly PG&E billSmaller PG&E billGenerator fuel, battery replacement down the road
Best fitLine is close and cheapLine is close, outages are commonLine is far, and you're ready to be your own utility
Questions to ask before you decide

As with septic and steep driveways, "alternative" tends to come with an alternative price tag, and here you're also signing up to be your own power company.

Who to call

Numbers from each agency's own website, checked November 26, 2026.

PG&E Building and Renovation

New electric service, line extensions, temporary construction power. Apply and track it online in Your Projects.

1-877-743-7782

PG&E Building and Renovation →

County Permit Center

Electrical, solar and battery permits go with your building permit. Small rooftop systems can use the streamlined solar permit.

(831) 755-5025 · 1441 Schilling Place, Salinas

Your fire agency

May require warning signs at solar equipment and generators, and reviews where batteries go.

Find your fire agency →
  1. 1

    Before you buy

      Ask before you make an offer
      • Where's the nearest PG&E pole or line, and is it on this side of the road?
      • Did the neighbors bring power in overhead or underground, and what did it cost them?
      • How often has this area been in a Public Safety Power Shutoff?
    • 2

      Can I build here?

      • 3

        Design

        • 4

          Permits

          • 5

            Build

            • 6

              Move in and beyond

              Real numbers

              What power actually cost, from readers. Every number has a year, because prices move.

              WhatCostSource
              PG&E average new-service costs and timelinesPG&E publishes averagesPG&E
              Backup generator$500 to over $10,000, depending on size (state estimate)CPUC
              PG&E line extension, per footNo reports yetShare yours
              Solar and battery system for a new homeNo reports yetShare yours

              Sources

              Every fact above links to its source. Checked November 26, 2026, and rechecked monthly.

              Not legal, electrical or financial advice. Utility rules and prices change. Confirm with PG&E, the county and a licensed electrician.

              Your checkmarks here also appear on the Project Map. See also Water (pumps need power) and Access (the line usually follows the driveway).